42.705 Final indirect cost rates.
-
(a) Final indirect cost rates shall be established on the basis of- -
(b) Within 120 days (or longer period, if approved in writing by the contracting officer,) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the contractor must submit a completion invoice or voucher reflecting the settled amounts and rates. To determine whether a period longer than 120 days is appropriate, the contracting officer should consider whether there are extenuating circumstances, such as the following:-
(1) Pending closeout of subcontracts awaiting Government audit. -
(2) Pending contractor, subcontractor, or Government claims. -
(3) Delays in the disposition of Government property. -
(4) Delays in contract reconciliation. -
(5) Any other pertinent factors.
-
-
(c) -
(1) If the contractor fails to submit a completion invoice or voucher within the time specified in paragraph (b) of this section, the contracting officer may--
(i) Determine the amounts due to the contractor under the contract; and -
(ii) Record this determination in a unilateral modification to the contract.
-
-
(2) This contracting officer determination must be issued as a final decision in accordance with 33.211.
-