42.503-1 Postaward conference arrangements.

  1. (a) The contracting officer who decides that a conference is needed is responsible for-

    1. (1) Establishing the time and place of the conference;

    2. (2) Preparing the agenda, when necessary;

    3. (3) Notifying appropriate Government representatives (e.g., contracting/contract administration office) and the contractor;

    4. (4) Designating or acting as the chairperson;

    5. (5) Conducting a preliminary meeting of Government personnel; and

    6. (6) Preparing a summary report of the conference.

  2. (b) When the contracting office initiates a conference, the arrangements may be made by that office or, at its request, by the contract administration office.