32.501-1 Customary progress payment rates.
-
(a) The customary progress payment rate is 80 percent, applicable to the total costs of performing the contract. The customary rate for contracts with small business concerns is 85 percent. -
(b) The contracting officer must--
(1) Consider any rate higher than those permitted in paragraph (a) of this section an unusual progress payment; and -
(2) Not include a higher rate in a contract unless advance agency approval is obtained as prescribed in 32.501-2.
-
-
(c) When advance payments and progress payments are authorized under the same contract, the contracting officer must not authorize a progress payment rate higher than the customary rate. -
(d) In accordance with 10 U.S.C. 3804(b) and 41 U.S.C. 4504(b), the limit for progress payments is 80 percent on work accomplished under undefinitized contract actions. The contracting officer must not authorize a higher rate under unusual progress payments or other customary progress payments for the undefinitized actions.