4.804-4 Physically completed contracts.
-
(a) Except as provided in paragraph (b) of this section, a contract is considered to be physically completed when--
(1) -
(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies; -
(ii) The contractor has performed all services and the Government has accepted these services; and -
(iii) All option provisions, if any, have expired; or
-
-
(2) The Government has given the contractor a notice of complete contract termination.
-
-
(b) Rental, use, and storage agreements are considered to be physically completed when--
(1) The Government has given the contractor a notice of complete contract termination; or -
(2) The contract period has expired.
-