44.203 Consent limitations.
-
(a) The contracting officerâs consent to a subcontract or approval of the contractorâs purchasing system does not constitute a determination of the acceptability of the subcontract terms or price, or of the allowability of costs, unless the consent or approval specifies otherwise. -
(b) Contracting officers shall not consent to--
(1) Cost-reimbursement subcontracts if the fee exceeds the fee limitations of 15.404-4(c)(4)(i); -
(2) Subcontracts providing for payment on a cost-plus-a-percentage-of-cost basis; -
(3) Subcontracts obligating the contracting officer to deal directly with the subcontractor; -
(4) Subcontracts that make the results of arbitration, judicial determination, or voluntary settlement between the prime contractor and subcontractor binding on the Government; or -
(5) Repetitive or unduly protracted use of cost-reimbursement, time-and-materials, or labor-hour subcontracts (contracting officers should follow the principles of 16.103(c)).
-
-
(c) Contracting officers should not refuse consent to a subcontract merely because it contains a clause giving the subcontractor the right of indirect appeal to an agency board of contract appeals if the subcontractor is affected by a dispute between the Government and the prime contractor. Indirect appeal means assertion by the subcontractor of the prime contractorâs right to appeal or the prosecution of an appeal by the prime contractor on the subcontractorâs behalf. The clause may also provide that the prime contractor and subcontractor shall be equally bound by the contracting officerâs or boardâs decision. The clause may not attempt to obligate the contracting officer or the appeals board to decide questions that do not arise between the Government and the prime contractor or that are not cognizable under the clause at 52.233-1, Disputes.