42.1104 Surveillance requirements.
-
(a) The contract administration office determines the extent of production surveillance on the basis of--
(1) The criticality (degree of importance to the Government) assigned by the contracting officer (see 42.1105) to the supplies or services; and -
(2) Consideration of the following factors:-
(i) Contract requirements for reporting production progress and performance. -
(ii) The contract performance schedule. -
(iii) The contractorâs production plan. -
(iv) The contractorâs history of contract performance. -
(v) The contractorâs experience with the contract supplies or services. -
(vi) The contractorâs financial capability. -
(vii) Any supplementary written instructions from the contracting office.
-
-
-
(b) Contracts at or below the simplified acquisition threshold should not normally require production surveillance. -
(c) In planning and conducting surveillance, contract administration offices shall make maximum use of any reliable contractor production control or data management systems. -
(d) In performing surveillance, contract administration office personnel shall avoid any action that may--
(1) Be inconsistent with any contract requirement; or -
(2) Result in claims of waivers, of changes, or of other contract modifications.
-