36.212 Preconstruction orientation.
-
(a) The contracting officer will inform the successful offeror of significant matters of interest, including--
(1) Statutory matters such as labor standards (subpart 22.4), and subcontracting plan requirements (subpart 19.7); and -
(2) Other matters of significant interest, including who has authority to decide matters such as contractual, administrative (e.g., security, safety, and fire and environmental protection), and construction responsibilities.
-
-
(b) As appropriate, the contracting officer may issue an explanatory letter or conduct a preconstruction conference. -
(c) If a preconstruction conference is to be held, the contracting officer shall--
(1) Conduct the conference prior to the start of construction at the work site; -
(2) Notify the successful offeror of the date, time, and location of the conference (see 36.522); and -
(3) Inform the successful offeror of the proposed agenda and any need for attendance by subcontractors.
-