28.103-1 General.
-
(a) Generally, agencies shall not require performance and payment bonds for other than construction contracts. However, performance and payment bonds may be used as permitted in 28.103-2 and 28.103-3. -
(b) The contractor shall furnish all bonds before receiving a notice to proceed with the work. -
(c) No bond shall be required after the contract has been awarded if it was not specifically required in the contract, except as may be determined necessary for a contract modification.