By cmsifyAdmin, 31 January, 2025 View Node 32.008 Notification of overpayment. 32.008 Notification of overpayment. If the contractor notifies the contracting officer of a duplicate payment or that the Government has otherwise overpaid, the contracting officer shall follow the procedures at 32.604. Parent topic: Part 32 - Contract Financing Log in or register to post comments Comments
32.008 Notification of overpayment. If the contractor notifies the contracting officer of a duplicate payment or that the Government has otherwise overpaid, the contracting officer shall follow the procedures at 32.604. Parent topic: Part 32 - Contract Financing
32.008 Notification of overpayment. If the contractor notifies the contracting officer of a duplicate payment or that the Government has otherwise overpaid, the contracting officer shall follow the procedures at 32.604. Parent topic: Part 32 - Contract Financing